The construction of the A904 Westbound carriageway has been the focus recently with a planned traffic management change planned in the near future. This will see a lane for traffic in each direction on both the Eastbound and Westbound carriageway. This change then facilitates the completion of the centre reserves.
Works continue at the Laurieston Road junction and on the A904 Westbound carriageway at Earl’s Gate and Westmains.
Traffic signal works have started in the Earl’s Gate roundabout area with existing traffic signals being replaced and new pedestrian crossing traffic signals installed. Traffic signal works will continue through the site with new crossings being opened to the public following commissioning.
Works are due to commence in the Westfield roundabout area with resurfacing of the roundabout planned to commence towards the end of November.