Work started on site on August 2023. Here we will be posting monthly project updates to keep you informed of progress.
Progress Report Soft landscaping works in the form of seeding and coir matt installation has continued across the site in the ponds and swales and will continue in the coming…Read More
Progress Night shift works completed all the planned utility crossings and temporary island surfacing. Throughout the site there are visible areas of temporary surfacing where islands have been shortened, removed…Read More
This summer, the A9/A904 Westfield project will reach a major milestone when work starts on the next phase of the initiative which aims to transform local infrastructure and boost the…Read More
The construction of the new carriageway embankments and footways has continued over the period from Midthorn to Earl’s Gate. Works continue during night shift throughout the site on the A9…Read More
Band Drain (PVD) installation has been completed across various areas of the site. These areas will be surcharged over the coming months with imported material to impose the required load…Read More
The construction of the permanent drainage ponds and swales continues with a number of these completed over the last few weeks. Works have re-commenced within the Stadium round about to…Read More
Leader of Falkirk Council, Councillor Cecil Meiklejohn, outlines the plans behind the Westfield improvement project. Earthworks for the new carriageway and for the permanent surface water drainage, in the form of…Read More
Due to the Christmas and New Year shut down there is no project update for January.
Re-surfacing works to Earl’s gate roundabout have been completed. Balfour Beatty would like to take this opportunity to thank everyone for their patience and understanding throughout the duration of these…Read More
Works are now well underway at the A9 A904 Improvements project. Re-surfacing work to upgrade Earl’s gate roundabout is progressing well and due to be complete by the end of…Read More