Monthly Updates

Work started on site on August 2023. Here we will be posting monthly project updates to keep you informed of progress.

September 2024

Progress Report Soft landscaping works in the form of seeding and coir matt installation has continued across the site in the ponds and swales and will continue in the coming…Read More

August 2024

Progress Night shift works completed all the planned utility crossings and temporary island surfacing. Throughout the site there are visible areas of temporary surfacing where islands have been shortened, removed…Read More

July 2024

This summer, the A9/A904 Westfield project will reach a major milestone when work starts on the next phase of the initiative which aims to transform local infrastructure and boost the…Read More

May 2024

The construction of the new carriageway embankments and footways has continued over the period from Midthorn to Earl’s Gate. Works continue during night shift throughout the site on the A9…Read More

April 2024

Band Drain (PVD) installation has been completed across various areas of the site. These areas will be surcharged over the coming months with imported material to impose the required load…Read More

March 2024

The construction of the permanent drainage ponds and swales continues with a number of these completed over the last few weeks. Works have re-commenced within the Stadium round about to…Read More

February 2024

Leader of Falkirk Council, Councillor Cecil Meiklejohn, outlines the plans behind the Westfield improvement project. Earthworks for the new carriageway and for the permanent surface water drainage, in the form of…Read More

January 2024

Due to the Christmas and New Year shut down there is no project update for January.

December 2023

Re-surfacing works to Earl’s gate roundabout have been completed. Balfour Beatty would like to take this opportunity to thank everyone for their patience and understanding throughout the duration of these…Read More

November 2023

Works are now well underway at the A9 A904 Improvements project. Re-surfacing work to upgrade Earl’s gate roundabout is progressing well and due to be complete by the end of…Read More