November 2023

Works are now well underway at the A9 A904 Improvements project. Re-surfacing work to upgrade Earl’s gate roundabout is progressing well and due to be complete by the end of November.

The site is now being secured with site perimeter fencing being installed and as a result pedestrian management is being implemented as per the “Pedestrian diversion routes” sign boards.

Site access points are currently being installed off the A904 and A9 in various locations under traffic management to allow safe access and egress to site going forward. Earth works to start forming the new carriageway and the installation of the permanent surface water drainage are due to start in November.